Please see attached instructions video for needed upgrade steps. Ensure circuit is done according to schematics:

View file
nameEVF_schematics_DRAWING_1477554_1_A.pdf
height250


Note! Only trained electrician can perform the needed on-site upgrade.

...

After physical device installation also the controller configuration is needed. Instructions for USB memory stick configuration work:

By this method: Deploy operator configuration to charger with USB stick configuration

With this file: 

View file
nameConfig_meter
height250



Instructions video (contains also instructions how to verify correct energy meter data communication with the controller electronics board):

View file
nameaviensto_evc_-_ensto_pro_(evf)_update_with_mid_energy_meters_720.mp4
height250

...